ERSO transformers for the Irkutsk region have successfully passed the tests

07.08.2023
The equipment is intended for operation at the Meget substation.

Employees of the holding's Ufa site assembled two TDTN-40000/110-UHL1 transformers. They will go to the Angarsk district of the Irkutsk region, to the Meget substation. Both units have been successfully tested. ERSO specialists will supply and supervise the installation of products.

During the construction of the Meget substation, the entire complex of construction and installation, electrical installation, commissioning, delivery and completion of the facility with materials was performed by BMU GEM LLC.

In the winter of this year, a delegation of this company, at the invitation of the ERSO management, visited the Ufa Transformer Plant. The guests were shown production lines, testing stations, and were told about the stages of transformer production.