The employees of the holding have successfully carried out acceptance tests (PSI) of the equipment.

Two TDTN-63000/110 U1 units were assembled by employees of the Ufa Transformer Plant. Soon they will be sent to the 110 kV Moinaki substation (Yevpatoria) to provide enterprises and the population with a stable power supply. ERSO will supply, unload and supervise the installation of equipment.

The operating voltage of the substation is 110/35/10 kV, the installed capacity is 37.6 MVA. There are four power transformers installed at the power facility.