ERSO shipped the second transformer for Inors substation

09.03.2023
ERSO shipped the second transformer for Inors substation

The holding's products will provide a stable power supply to the Ufa microdistrict of the same name.

The walls of the Ufa transformer plant left the second transformer TDN-25000/110-UHL1, manufactured for the 110 kV Inors substation. Thanks to the operation of the new equipment, about 75 thousand residents of the capital of Bashkiria will receive uninterrupted electricity.

About 850 million rubles were invested in the construction of the Inors Substation. As part of the project, a 2.6-kilometer cable power line is also being built to feed the substation.

Recall that the construction of Inors began in August 2022. The project is scheduled to be completed by the end of 2023.