ERSO prepares reactors for Agorta substation for testing

19.05.2023
In total, the holding will manufacture seven units for this substation.

Employees of the Moscow Electrozavod assembled two ROMBSM-60000/500-UHL1 reactors. The equipment is intended for operation at the 500 kV substation "Agorta" (Zeysky district, Amur region). Soon the cars will go to the test. After shipment, ERSO employees will deliver, unload and supervise the installation of the units.

ROMBSM shunt reactors are designed to compensate for reactive power and stabilize the voltage level in high-voltage electrical networks with voltages from 6 to 1150 kV.

The Agorta substation is located near the Zeya reservoir - this hydro-object is one of the largest in Russia in terms of its volume and area.

ERSO готовит к испытаниям реакторы для ПС «Агорта».jpg